Why my tasks or milestone dates don't match with the Gantt graphic view (the bar ends one day before the real end of task)?

Re: The Gantt graphic view.

Posted: Wed Oct 01, 2014 1:12 pm
by Alexander
Hello,

Please note, it is a feature of displaying.
Deadline is starting in 00.00 of this day, that's why this task is displayed like overdue and doesn't display in Gantt graphic.

Re: The Gantt graphic view.

Posted: Fri Oct 03, 2014 6:37 am
by mayank@smartysoft.in
Hi Folks Can n't we introduce some coloring pattern in Gantt Chart ?

Re: The Gantt graphic view.

Posted: Fri Oct 03, 2014 7:44 am
by Alexander
Hello,

ONLYOFFICE Gantt Chart gives you the panoramic view of all the project activities and their status:
Blue - open task/milestone, green- closed task/milesone, red - overdue task/milestone.

Please follow the link below to find a guide "HOW TO MANAGE YOUR PROJECT USING THE GANTT CHART?":
http://helpcenter.onlyoffice.com/guides ... chart.aspx

In the current version of OnlyOffice there is no possibility to introduce another coloring pattern in Gantt Chart.
We will definitely forward your suggestion to our development team for further consideration.